Rooppur unit begins trial supply of 350MW to national grid

Daily Sun Report, Dhaka

Published: 18 Nov 2026, 12:00 AM

Rooppur unit begins trial supply of 350MW to national grid
A A

Nuclear-generated electricity was connected to the country’s national grid for the first time on Tuesday, when 350 megawatts (MW) from the first unit of the Rooppur Nuclear Power Plant in Ishwardi, Pabna, began flowing at 3:16pm on a trial basis.

The supply is not commercial production. 

According to a press release issued by the project on Tuesday, it has been started primarily to test equipment and operational systems and their coordination with the grid. 

Fakir Mahbub Anam, MP, minister for posts, telecommunications and information technology and minister for science and technology, was present.

Under the initial trial connection, electricity will be supplied for around eight to 10 hours, during which tests will assess the turbines, generators and integrated operational systems. The plant will then be disconnected for further tests and, after a break of around 28 hours, reconnected for four to six hours to complete the necessary technical and operational checks.

Plant sources said the phased increase in generation capacity is proceeding in line with International Atomic Energy Agency (IAEA) guidelines and standards. 

The reactor vessel, turbines, generators, other key equipment and automated control systems will be examined. The unit may be shut down temporarily when necessary, and generation and supply may be raised or reduced during the process.

The press release said uninterrupted and stable supply cannot be ensured during the trial phase. The Power Grid Company of Bangladesh (PGCB) will take measures to maintain grid balance as generation and supply fluctuate, while officials of the Bangladesh Power Development Board (PDB) will monitor the supply.


Plant officials said trial generation could continue for several months. To raise output gradually to 100%, the plant needs licences and approvals from the Bangladesh Atomic Energy Regulatory Authority (BAERA), to which a report on test results will be submitted. Further increases will follow its approval. Under the agreement with the Russian contractor, commercial supply from the first unit at full capacity will begin after a 10-month trial operation.

With supply under way, Bangladesh has moved towards becoming the world’s 33rd country to generate nuclear power, though formal recognition is linked to the start of full-scale generation and supply. 

In October 2023, Rooppur was recognised as a nuclear facility after nuclear fuel arrived at the site, and Bangladesh was added to the list of countries possessing nuclear energy.

Rooppur is the largest single project in the country’s history. The Bangladesh Atomic Energy Commission, under the Ministry of Science and Technology, is implementing it, and the state-owned Nuclear Power Plant Company Bangladesh Limited (NPCBL), under the commission, operates the plant. Russian contractor Atomstroyexport is building two units of 1,200MW each, with a combined capacity of 2,400MW.

The project was initially scheduled for completion by December 2025, but its tenure has been extended twice, to June 2028. The extensions were made in accordance with the agreement with the contractor, and the project cost has not been increased on that account. However, the depreciation of the taka against the US dollar has raised expenditure by Tk26,000 crore, bringing the total cost to Tk1,38,686 crore.