Padma Rail Link
Test run on Bhanga-Rupdia route begins
UNB, Jashore
Published: 30 Mar 2024, 10:22 PM
The test run of a train on the Bhanga-Rupdia route commences on Saturday as part of the Padma Bridge Rail Link project. The stone-laden trial train departs from Bhanga in Faridpur at 8:41am and reaches Rupdia in Jashore at 10:20am. -Focus bangla
The test run of a train on the Bhanga-Rupdia route began on Saturday from Bhanga Junction in Faridpur district as part of the Padma Bridge Rail Link project.
The train left for Jashore’s Rupdia from Bhanga at 8:41am, said Bhanga Rail Station Master Zillur Rahman.
Md Shakhawat Hossian was the locomotive driver of the train, and it ran at 120 km/h, he said, adding that it took only one hour to reach Rupdia.
The train will leave for Bhanga from Rupdia Rail Station today, and it will run on the route for some days on an experimental basis, said Zillur.
A festive mood is prevailing among people over the operation of the train service on the Bhanga-Rupdia route.
The trial train run is being conducted under the observation of the Bangladesh Army and high-ranking officials of the rail project.
Already, a train on the Dhaka-Jashore route has launched, and the last portion of the project is Bhanga-Jashore, which is 87.32 km long.
On 14 October 2023, Prime Minister Sheikh Hasina opened the construction work on a rail link between Dhaka and Jashore under the ‘Padma Bridge Rail Link Construction Project.’
The railway line is being constructed in three phases (plus a 3km link being built between Dhaka and Gandaria): a 37km Gandaria-Mawa section, a 42km Mawa-Bhanga section, and an 87km Bhanga Junction-Jashore section. Some 43.2km of loops, siding, and Y-connections bring the total track length to 215.2km.
The entire railway project from Dhaka to Jashore is scheduled to be completed by June 2024.
There will be 20 stations from Dhaka to Jashore, of which 14 are new and 6 are already there. The previous stations are also being modernised. Once completed, trains will be able to run at a speed of 120 to 130 kilometres.
According to the railway sources, the Padma Bridge Rail Link project, a 172-km railway link being built to connect capital Dhaka to Jashore in the country’s south-west, is on course to be completed in June 2024.