If you have heard more about the India–Middle East–Europe Economic Corridor lately, you may be picturing containers moving between India and Europe by ship and train. That is the plan’s biggest promise. It may also be the part that takes the longest to deliver.
IMEC is about more than moving goods. The agreement
announced at the 2023 G20 summit also sets out plans for digital and electricity
cables, and a pipe to export clean hydrogen. Each would serve different
customers and need its own funding. There is no reason to judge all of them by
the railway’s timetable.
That matters when we talk about progress. A cable
that secures investment and provides a useful connection would be an
achievement in its own right. It would not mean the freight route was ready,
just as delays to the railway would not necessarily stop a separate digital
project.
Donald Trump’s renewed support has brought IMEC back
into focus as governments look for routes less exposed to disruption. The
interest is understandable. For businesses, though, the useful questions are
more specific: what is being built, who is paying for it, and when can
customers use it?
Different projects, different customers
A digital cable and a freight railway need to prove
themselves in different ways. A cable needs connections at either end and
customers willing to pay to use it. A freight service needs ships, trains,
ports and border crossings to work together each time a shipment moves.
There is a defined digital project associated with
IMEC’s wider aims. An EU Global Gateway document places the planned 9,000km
Blue Raman subsea cable within the corridor’s digital framework and lists €400
million in investment, including €37 million from the EU.
Those figures give us something concrete to discuss.
They do not tell us that IMEC’s railway has been funded or built. They do not
mean its planned electricity and hydrogen links are ready, either. Each project
must stand up to its own commercial test.
For freight, that test is demanding. A container
would leave India by ship, be moved onto a train at a Gulf port, travel towards
the Mediterranean and then return to a ship for Europe. Every transfer adds
time and cost. To attract customers, the whole journey must offer an advantage
over shipping the container by sea.
Ships already connect India, the Gulf and Europe.
The overland section is what would give businesses a different route. The UAE’s
freight railway reaches its border with Saudi Arabia, but a working rail
connection through to the Mediterranean is still missing.
A 2025 Atlantic Council study identified the
proposed connection involving Saudi Arabia, Jordan and Israel as a major gap.
It estimated a funding shortfall of $4.86 billion to $5.18 billion for a basic
UAE-to-Haifa freight route. That is an estimate for one section, not an agreed
budget for the entire corridor.
A second route must be dependable
Disruption has made the case for another trade route
easier to understand. If a company’s usual shipment is delayed, a reliable
alternative could help it keep supplies moving. But an alternative is useful
only if it works when needed.
The proposed IMEC route would not avoid every risk
at sea. Cargo sailing to a port inside the Gulf could still need to pass
through the Strait of Hormuz. The Atlantic Council has identified access
through Oman to the Arabian Sea as one possible way to reduce that exposure,
though it would need an effective connection to the rest of the route.
Rail would bring its own challenges. Countries would
have to agree on border procedures and charges, while operators would need
schedules shippers could rely on. Building the track would be a major step, but
it would not, on its own, create a service businesses can book.
That is why it makes sense to assess IMEC one
project at a time. If a digital link secures customers, it can move ahead while
governments work through the rail questions. The same could apply to an
electricity connection or hydrogen pipe if either has funding and buyers.
Progress on those projects would be real, even without a complete freight
route.
European Commission President Ursula von der Leyen
captured the political urgency in April 2026. “And now is the time to advance
promising connectivity projects like the IMEC,” she said while calling for more
ways to move exports without relying solely on the Strait of Hormuz.
The task now is to turn that support into projects
whose costs, customers and schedules are clear. IMEC could provide useful
connections before its trains run. We will understand its progress better if we
give each completed link credit for what it does, while being just as clear
about what is still on the drawing board.