Tk99.5cr project fails to ease woes on Sunamganj road

Jahangir Alam

Jahangir Alam

Published: 23 Nov 2026, 12:00 AM

Tk99.5cr project fails to ease woes on Sunamganj road
A A

The 8-km Tahirpur-Badaghat road in Sunamganj has become increasingly dangerous as repair work remains stalled in one section and moves slowly in another.
Potholes and erosion have left much of the road in poor condition, while soil dumped over damaged stretches has created dusty conditions and increased the risk of accidents for commuters.
The road connects Tahirpur upazila headquarters with Badaghat Bazar and is used by residents of four unions to travel to the upazila hospital, colleges, customs stations and major tourist attractions, including Shimul Bagan, River Jadukata, Barek Tila and Shaheed Siraj Lake.
According to the upazila Local Government Engineering Department (LGED) office, the road repair project was tendered on 4 October 2023, and divided into two packages.
The first package, covering Tahirpur Sadar to Hushnarghat, was approved at Tk6.5 crore, while the second, from Hushnarghat to Sundarpahari, was awarded to Dhaka-based Nabarun Construction at Tk93 crore.
However, work on the first package has not yet started, although more than two years have passed since the tender. The LGED has applied to cancel the contract and plans to invite a fresh tender. Work on the second package is underway but progressing slowly, according to local residents.
As the road has deteriorated, vehicles frequently suffer damage and commuters face accidents. The connecting section of Takatukia Bridge has also become risky due to soil erosion.
Autorickshaw driver Faruk Mia said commuters are being forced to risk their lives as there are potholes and eroded sections at several points. Motorcycle rider Jasim Uddin said the road becomes even more difficult to use during the rainy season, when people have to cross parts of the route by boat. During the dry season, the unpaved sections turn dusty and create severe traffic problems.
Upazila Engineering Officer Zahidul Islam said the LGED had applied to cancel the contract for the Tahirpur Sadar-Hushnarghat section as the contractor failed to start the work. “The contract will be cancelled soon, followed by a fresh tender. We hope to start the work as soon as possible to ease public suffering,” he said, urging the contractor working on the other package to complete the project quickly.
Tahirpur Upazila Executive Officer Ripamoni Devi said the road is very important and assured that she would contact the relevant authorities to take necessary steps to improve its condition.