SUST development projects proceed at snail’s speed
Daily Sun Report, SUST
Published: 21 Nov 2026, 12:00 AM
The second phase of the development project at Shahjalal University of Science and Technology (SUST) in Sylhet has achieved 48.45% overall progress, with several major construction works lagging behind schedule. The project may require an additional one to one-and-a-half years for completion.
SUST Chief Engineer Dr Mohammad Shahidur Rahman said applications had been submitted in September seeking extensions for the delayed projects.
"We have requested extensions of one to one-and-a-half years, depending on the individual projects," he said.
A total of 16 projects have been awarded to different contractors under the ongoing development scheme. M Jamal & Company received the highest number of contracts, securing six projects worth nearly half of the total allocation.
According to project data up to 15 November, nine of the 16 projects have achieved more than 50% progress, while the remaining seven are still below that level. Progress ranges from 19.76% to 67.86%.
The first contract was signed on 17 October 2024, while the last was awarded on 24 September 2025. The deadlines for six projects have already expired, while most of the remaining projects are scheduled for completion by December this year.
Among the major projects, construction of the 10-storey boys' dormitory has achieved 46.12% progress, although its contractual deadline expired on 31 October. The 10-storey girls' hall, has recorded only 19.76% progress. Its completion deadline is 21 December. Besides, the seven-storey international hall, has achieved 24.63% progress against its 23 December deadline.
Meanwhile, construction of Academic Building-1 and Academic Building-2 has progressed by 61.77% and 62.27%, respectively. The 10-storey Academic Buildings-3 and 4, have achieved 55.72% and 59.10% progress respectively.
The six-storey university school and college building has recorded the highest progress at 67.86% which is scheduled for completion on 30 December.
Construction of the central workshop has reached 51.83%, although its deadline expired on 3 September 3. The 10-storey club complex, has made only 18.66% progress against its 30 December deadline. The 10-storey administrative building has achieved 29.07% progress, despite its scheduled completion date of November 15.
The 11-storey teachers' and officers' residential building has recorded 55.60% progress, while construction of the 33/11 KV electric substation has reached 62.82 per cent.
Other projects include two 15-metre-span bridges, with 66.28% progress; expansion of the central garage, with 45.84% progress; and construction of a four-storey hall mosque, with 47.94% progress.