Six years on, Jhenaidah-Jashore six-lane project far from completion

Sheikh Ruhul Amin

Sheikh Ruhul Amin

Published: 18 Nov 2026, 12:00 AM

Six years on, Jhenaidah-Jashore six-lane project far from completion
A A

The Jhenaidah-Jashore six-lane highway project has fallen into uncertainty as only 12% of the work has been completed in six years, despite the project cost rising from Tk4,187 crore to Tk6,626 crore.
The 47.48-kilometre project, aimed at improving connectivity in the southwestern region, has been hampered by delays in land acquisition, allegations of irregularities and slow progress by contractors. Meanwhile, potholes at different points of the highway are causing suffering to passengers and transport operators and increasing the risk of accidents.
The Executive Committee of the National Economic Council (ECNEC) approved the project on 24 November 2020, under the Western Economic Corridor and Regional Enhancement (WECARE) Phase-1 project. It covers the road from Chanchra Checkpost in Jashore to Jhenaidah Central Bus Terminal. The project includes a four-lane main carriageway, two service lanes, four major bridges, 55 culverts, flyovers and other infrastructure. Around 304 acres of land are required for the project, but the Roads and Highways Department is yet to acquire all the required land.
Land acquisition has also been marred by allegations of irregularities in valuation. In some areas, land prices were allegedly assessed below market rates, while investigations found overvaluation of land and structures in other places. The project was scheduled for completion by December 2026. A decision on extending the project period is expected at the next World Bank meeting.
An investigation report submitted to the district administration on 4 January 2026, identified alleged overvaluation involving at least 36 plots and structures and confirmed 12% progress of the project in the past several years. The report also found unusually low valuations in areas including Barbazar, Raghunathpur, Ambagan, Dulalmundia and Malliknagar.
District administration officials said around 45% of land acquisition had been completed in Kaliganj and 50% in Jhenaidah Sadar. Additional District Commissioner (Revenue) Subir Kumar Das said land acquisition progress would exceed 60% within three weeks. “There is no negligence on the part of the district administration in this regard,” he said.
However, Nilan Ali, sub-divisional engineer of Lot-1, said delays in land acquisition had affected the start of construction. Work in the lot has progressed by around 10%, he said.
Engineer Tuhin Al Mamun, project manager of Lots 2 and 3, said construction remained slow even where land had already been handed over. “Despite repeated requests and letters, the contractor has failed to increase the pace of work,” he said. World Bank officials also expressed dissatisfaction with the slow progress during a visit to the project area on 19 July. The highway is an important route for goods transported from Bhomra, Benapole and Mongla ports. However, potholes at several points are disrupting traffic and increasing accident risks.
Osman Gani, a transport owner, said the road had become dangerous because of the contractors' negligence. “Accidents are occurring regularly, while passengers and transport operators are suffering immensely,” he said.
Attempts to contact representatives of the contracting companies for comments were unsuccessful.
Jhenaidah Deputy Commissioner Md Noman Hossain said the district administration was working to expedite land acquisition and project implementation. “Compensation cheques are being handed over to affected landowners in phases,” he said.