70.92% work on metro rail Kamalapur section completed
As of December 2025, all 177 piles, pile caps, piers and station columns have been completed
BSS, Dhaka
Published: 05 Feb 2026, 07:12 PM
File Photo
The extended Kamalapur section of the metro rail was 70.92% complete as of 31 January, and authorities aim to finish the 1.16-kilometre stretch by next year.
“The physical work on the Motijheel-to-Kamalapur
section of the Dhaka Metro Rail project has progressed rapidly,” Project Director
of Metro Line-6, Brig Gen (retd) Md Abdul Wahab, said on Thursday.
He said electric devices such as automated doors,
the signaling system and other equipment will be brought next year, adding,
“The section is expected to commence commercial operations in April or May next
year.”
“Track installation work will be completed within
the next two to three months,” the project director said.
Earlier, Managing Director of Dhaka Mass Transit
Company Limited (DMTC) Faruque Ahmed said the Kamalapur section will open on 1
January 2027, as system and track preparation work is progressing in full
swing.
According to the metro project, as of December 2025,
all 177 piles, pile caps, piers and station columns have been completed.
Besides, all precast parapet walls have been
installed, while the station’s steel roof structure and steel erection work
have been completed, it said.
Project details show that 2,800 square metres of
brick wall and plaster work at the concourse level have been completed.
The project authorities are carrying out intensive
construction activities, including agreements for installing electrical and
mechanical systems.
Meanwhile, the government has saved Tk185 crore from
electro-mechanical work on the metro rail, particularly on the
Motijheel-Kamalapur section.
As of 31 December 2025, the overall progress of the
Uttara North–Motijheel section reached 99.97%, while the Motijheel-Kamalapur
section recorded 69.85%.
The total length of Bangladesh’s first Mass Rapid
Transit (MRT) Line, running from
Diabari–Uttara–Mirpur–Agargaon–Farmgate–Shahbagh–Dhaka University–Motijheel–Kamalapur,
is 21.26 kilometres.
Commercial operation of the metro rail from Uttara
to Motijheel began in November 2023.