For fourteen years, people travelling between Gazipur and Dhaka's airport waited for a rapid bus service that never arrived. On 18 October, the cabinet decided to abandon the Bus Rapid Transit (BRT) scheme and convert the 20.5-kilometre corridor into a conventional six-lane road. The plan includes removing stations and the barriers separating the bus lanes. Two overpasses are also being considered for widening. Approved in 2012 at an estimated Tk 2,038 crore, the project later acquired a revised budget of Tk 4,268.32 crore. About Tk 2,811 crore has already been spent. Those figures describe a vast commitment of public resources, yet they do not tell commuters what will happen to their daily journeys. The years of construction brought traffic disruption to a road used by workers, traders and long-distance travellers. Now the promised service has been abandoned before carrying a passenger. There are legitimate reasons to question whether such a troubled project should continue. There are also serious costs in dismantling what has been built. The decision therefore needs to be judged on its likely results, not on the relief of finally reaching one.
The argument over cancellation has produced two very different descriptions of the same corridor. By December 2024, about 97 per cent of the infrastructure work had been completed, while overall physical progress was 77.48 per cent. That distinction matters. A station without a bus is not a transport service. Two attempts to procure the required buses failed. A review team from Bangladesh University of Engineering and Technology (BUET), led by Professor Shamsul Hoque, recommended abandoning BRT operations. It cited serious design problems. Passengers heading beyond the airport would have to change buses. The stations were designed for buses with doors on the right, limiting integration with Bangladesh's ordinary bus fleet, whose doors are on the left. Yet, the Institute for Planning and Development has urged the government to reverse its decision. It argues that completing the corridor would preserve investment in mass transit. Neither position can be accepted on construction percentages alone. The money already spent cannot justify every additional expense. Equally, the faults identified by experts do not prove that a wider highway will serve passengers better. The missing piece is a public comparison of the remaining costs, operating requirements and likely benefits of each practical option.
There is useful international evidence on what successful bus investment can achieve. In December 2023, the World Bank reported that Dar es Salaam's first BRT phase had cut travel time on a corridor of almost 16 kilometres from more than two hours to less than one between 2016 and 2022. A separate World Bank review published in March 2024 reported that BRT infrastructure supported by the Lagos Urban Transport Project 2 had reduced public transport costs by around 30 per cent for 200,000 daily passengers during 2010–2017. Those figures are not promises for Gazipur. Both cities had different networks, passenger demand and operating arrangements. They do show why transport projects should be evaluated through the passenger experience. How long does a journey take from home to work? How many changes are required? Can passengers afford the fare? Is the service safe and dependable? A wider road could improve movement, but its impact will depend on how road space is used and whether buses receive reliable access. Six lanes on a drawing cannot answer these questions. Bangladesh needs credible forecasts for travel times, passenger numbers and operating costs under the conversion plan, alongside an assessment of whether any form of bus priority remains feasible.
The failure also calls for an account of the decisions that brought it about. An Asian Development Bank report issued in November 2022 identified underestimation of civil works costs at appraisal, changes in project scope and design, and cost escalation linked to delays. These were concrete problems in planning and implementation, not simply a missed deadline. In July 2025, the Executive Committee of the National Economic Council rejected a proposal to raise the project's cost to about Tk 6,598 crore and extend it to 2029. By then, the consequences had gone well beyond the budget. Reports say seven people died in construction-related accidents. Five were killed when a girder fell onto a vehicle in Uttara in August 2022. A serious review must examine early feasibility work, contract management, safety supervision and the response to warnings. It should make clear which decisions were defensible at the time and which fell short of professional duties. Finding that a project failed is not the same as proving misconduct by a particular person. But leaving the chain of decisions unexplained would make the next costly mistake easier to repeat. Publicly funded infrastructure deserves a public record of what happened.
The cabinet has asked officials for an initial progress report within fifteen days, followed by monthly updates. Those reports should be more than lists of demolition tasks. As conversion moves forward, the authorities should explain what can be reused, how much the work will cost and what legal or financial obligations remain with development partners. They should publish a safety plan for pedestrians and arrangements to keep existing buses moving during construction. Most importantly, they should set targets that passengers can verify: journey time at peak hours, waiting time, fares and safe access to stops. Professor Hoque has also proposed stronger commuter rail links between Gazipur and Dhaka. That option deserves its own assessment, not a promise made to soften the loss of BRT. The people who depend on this corridor need a workable service now, while longer-term proposals are studied. The government has the authority to abandon a project that no longer makes economic or practical sense. It also carries the burden of showing why the replacement is worth its cost. On an ordinary working morning, a commuter will care little about whether the road was once called BRT. The question will be whether getting to work has become quicker, safer and less expensive. That is the result by which this decision should be remembered.