Govt set to sign deal with Japanese firms by 30 Nov for operating Dhaka airport’s 3rd terminal
Daily Sun Report, Dhaka
Published: 23 Nov 2026, 11:51 PM
Photo: Collected
The government aims to sign an agreement with a Japanese
consortium by 30 November to operate the third terminal of Hazrat Shahjalal
International Airport in Dhaka, and launch partial operations with four flights
on 16 December.
Afterwards, it would likely take up to 14 months to begin
full-scale operations, said Civil Aviation and Tourism Minister M Rashiduzzaman
Millat on Monday, while updating reporters about the launch plans.
He addressed reporters after emerging from a meeting at the
Secretariat.
Prime Minister’s Special Assistant Barrister Gias Uddin and
Civil Aviation and Tourism Ministry Secretary Nurunnahar Chowdhury were
present.
The minister said the concerned government committee
approved the concession agreement, covering the operation and management of the
third terminal, on Monday.
Earlier in the day, the Cabinet Committee on Economic
Affairs, chaired by Finance and Planning Minister Amir Khosru Mahmud Chowdhury,
approved the deal at a meeting in the Secretariat.
As per the deal, the Japanese consortium comprises Japan
Airport Terminal Co Ltd, Sumitomo Corporation, Nippon Koei and Narita
International Airport Corporation.
Another Japanese entity, the Japan International Cooperation
Agency (JICA), has already provided crucial assistance in constructing the
third terminal.
Initially, the terminal will handle four flights – two
arrivals and two departures – operated by the Biman Bangladesh Airlines. The
number of flights will gradually increase, while discussions are underway to
add flights to Singapore and other destinations.
Millat said the terminal was initially planned to open at
25% capacity, but the consortium would not be able to operate at that level
immediately. As a result, operations will begin with four flights. He said
international airports generally ramp up operations in phases.
Built at a cost of more than Tk21,000 crore, the third
terminal has remained unused for around 23 months despite being nearly 99%
complete.
Once fully operational, it is expected to double or nearly
triple the airport’s passenger flow, and triple its cargo-handling capacity.