Nuclear power added to national grid for the first time
Daily Sun Report, Dhaka
Published: 17 Nov 2026, 04:06 PM
Nuclear
power was added to the national grid for the first time on Tuesday afternoon after
the Rooppur Nuclear Power Plant (RNPP) in Pabna supplied 350-megawatt electricity
on a trial basis.
The first
unit of the power plant would supply electricity for 8-10 hours at a stretch to
undergo operational tests.
Afterwards,
the supply would be halted for conducting technical examinations, and after 28
hours, the supply would be started again for a brief period of 4-6 hours to run
further technical and operational tests, said a press release issued by the
power plant.
Retail
users would get to use nuclear power every time RNPP supplies to the national
grid, according to the release.
Science and Technology Minister Faqir Mahbub Anam was present at the power plant when the first supply to the grid was initiated on Tuesday.
During the
first 8-10-hour supply, the first unit’s reactor, turbine, generator and other
equipment would be tested for operational effectiveness.
After
completing all the necessary technical and operational tests, the supply would
be gradually increased to 100% capacity, which is 1,200-megawatt in each unit
of the two-unit nuclear power plant.
Before
starting the process to increase supplies to the national grid, the RNPP authority
would seek the approval of Bangladesh Atomic Energy Regulatory Authority
(BAERA).
According
to an agreement with the Russian construction company Atomstroyexport (ASE),
RNPP authority would gradually increase the supply to 100% capacity during a
10-month trial and test period.
Afterwards,
BAERA would provisionally take over as the operating company of the power plant’s
first unit. Then the government would issue a formal notification, announcing the
state-run Nuclear Power Plant Company Bangladesh Ltd (NPCBL) as the final
operating company of the first unit.