Govt moves to ensure safe water, sanitation in Barind region
BSS, Dhaka
Published: 24 Oct 2026, 12:00 PM
Photo: Collected
The government has initiated a big move to expand safe water supply and sanitation facilities in 123 upazilas across 16 districts of the Barind region under Rajshahi and Rangpur divisions under a project with an estimated cost of Tk1,203.73 crore.
The Local Government Division has proposed the project,
titled “Safe Water Supply and Sanitation Project in the Barind Region”, for
implementation by the Department of Public Health Engineering (DPHE) from
October 2026 to March 2030, with full government funding.
“The project will improve public health and living standards
in the greater Barind region through the expansion and development of safe
water supply and sanitation facilities,” the Planning Commission said in its
project summary prepared for consideration by the Executive Committee of the
National Economic Council (ECNEC).
The project will be placed before the next meeting of the
Executive Committee of the National Economic Council (ECNEC), scheduled to be
held tomorrow at the Bangladesh Secretariat, with ECNEC Chairman and Prime
Minister Tarique Rahman in the chair.
Talking to BSS, a senior Planning Commission official said
the project proposes 59,778 improved twin-pit latrines for low-income
households, 4,394 community-based water supply units, 22,176 shallow tubewells
and 4,829 deep tubewells.
It also includes 5,399 shallow tubewells with submersible pumps and reservoirs, 1,113 deep tubewells with submersible pumps and reservoirs, 125 public toilets, 1,068 ring wells and 1,797 rainwater harvesting systems.
The plan also provides for the re-excavation of ponds and
construction of 16 pond sand filters.
According to the project document, the Barind region ranks
second among six water-availability hotspots identified in the Bangladesh Delta
Plan 2100.
“Climate change, excessive groundwater extraction and
inadequate groundwater recharge are making the shortage of safe water in the
Barind region increasingly acute,” the official said.
Groundwater levels decline during the dry season, creating
shortages of drinking water and irrigation water across large parts of northern
Bangladesh. The situation improves to some extent during the monsoon, it added.
The document also reported that only 63.6% of the population
in the region has access to basic sanitation facilities. Inadequate sanitation
increases the risk of waterborne diseases and environmental pollution,
threatens public health and reduces productivity, thereby hindering
socioeconomic development.
The commission selected all upazilas in Rajshahi and Rangpur
divisions for the project because of recurring drought, irregular rainfall,
declining groundwater levels and limited access to safe water sources. Climate
change and population growth have further intensified these challenges.
The project proposes annual allocations of Tk292.93 crore
for fiscal year 2026-27, Tk350.37 crore for 2027-28, Tk367.58 crore for 2028-29
and Tk192.85 crore for 2029-30.
The project evaluation committee recommended approval at a
meeting on January 26, 2026, subject to compliance with its decisions.
The Planning Commission said the project also aligns with
the election manifesto commitment to develop modern and safe communities
through safe water supply and waste management.
As the estimated cost exceeds Tk50 crore, the project
requires ECNEC approval under the government’s development project formulation,
processing, approval and revision guidelines issued in June 2022.
After completing all other necessary procedures, the
commission has recommended placing the project before ECNEC for consideration
and approval.