85% of Ctg to escape waterlogging as mega project work ends in Feb
Nur Uddin Alamgir, Chattogram
Published: 19 Nov 2026, 12:00 AM
An aerial view shows canal re-excavation work in Bakalia, Chattogram. The project aims to address the port city’s longstanding waterlogging problem and is expected to be completed in February. The photograph was taken on Wednesday. - RABIN CHOWDHURY
Around 85% of Chattogram city is expected to remain free from waterlogging during the next rainy season as a Tk8,626.62 crore mega project to address the long-standing crisis is nearing completion in February.
However, sustaining the benefits will depend on regular maintenance of the 36 canals being re-excavated and widened under the project titled “Re-Excavation Expansion, Renovation and Development of Khals for Mitigating Water Logging Problems in Chattogram City”.
Complete elimination of waterlogging will require re-excavation, widening and cleaning of all major and branch canals that drain rainwater into rivers and the sea, project sources said.
Overall project progress has reached 96%, with work on 30 of the 36 canals completed. Five others are 96% complete, while Hizra Khal has achieved 68% progress.
Project Director Lieutenant Colonel Mohsinul Hoque Chowdhury of the Bangladesh Army's 34 Engineering Construction Brigade told the Daily Sun that work on Hizra Khal was expected to finish by 30 January next year.
Of 11 land acquisition cases, compensation for one is being distributed, six have received ministry approval, and the remaining four are expected to be approved within three months.
“However, although the physical works of the project will be completed by February, we sought an extension until June 2028 to complete the compensation process,” he said.
“We will ensure that every concerned person receives compensation under the project,” he assured.
“We will start the process of handing over the project to the Chattogram City Corporation (CCC) from March for maintenance. We will assist the CCC for a period of one and a half years after the handover,” he said.
Highlighting the project's benefits, the PD said around 85% of areas surrounding the 36 renovated canals would remain waterlogging-free next rainy season.
“If the canals can be kept clean through regular maintenance, the benefit can be sustained for the next 20 to 30 years,” he said.
However, making the entire city waterlogging-free will require similar work on all canals and their branches.
Delayed and improper implementation of previous waterlogging mitigation projects, coupled with inadequate maintenance, has led to repeated waterlogging. Residents of many low-lying areas suffered for several days at different times during the last rainy season.
The Chattogram Development Authority (CDA), CCC and Bangladesh Water Development Board (BWDB) are implementing four mega projects worth around Tk14,400 crore to tackle waterlogging and protect the city from tidal surges.
The CDA is implementing two projects, including the largest one, worth Tk8,626 crore. Its other project, involving Tk2,779 crore, is for constructing an 8.55km road along the Karnaphuli River from Kalurghat Bridge to Chaktai Khal. It has achieved around 90% progress.
The CCC's Tk1,362 crore project to excavate a new canal from Baroipara to the Karnaphuli River has also crossed 95% progress. Approved in 2014, the project aims to improve drainage.
The BWDB, with Army support, is implementing a Tk1,620 crore project titled “Controlling Flood, Addressing Waterlogging and Development of Drainage System in Chattogram City”. Approved in 2019, it has achieved over 95% progress, sources said.
Following the recurring waterlogging, the Local Government Ministry formed a 19-member committee headed by CCC Administrator Dr Shahadat Hossain, with representatives of various service providers.
Acting on the committee's recommendations, the CCC is planning two more projects costing Tk3,871 crore: Tk322 crore for maintaining and renovating the 36 canals and Tk3,549 crore for renovating and developing 21 canals excluded from ongoing projects.
The main Tk8,626.62 crore project was approved by ECNEC on 9 August 2017. The CDA signed a memorandum of understanding with the Bangladesh Army on 9 April 2018 for civil works worth Tk5,498.59 crore.
Although its deadline expired on 30 June this year, the implementing agency has sought a two-year extension.
The project includes 58.37km of roads, 162.994km of RCC retaining walls, 21.02km of side drains, 220 cross-drain culverts, 19.7km of footpaths and 21 silt traps. It also involves widening 44.14km of fixed roadside drains, replacing 115 culverts and PC bridges, and installing six tidal regulators and 13 pump.