The government on Tuesday okayed the proposal for setting up a new composite brigade of Bangladesh Army at Padma bridge site to ensure the country’s biggest under-construction infrastructure’s safety and security.
The project "Establishment of 99 Composite Brigade for Safety and Security of Padma Multipurpose Bridge" will be implemented on 115 acres of land on both the sides of the mega infrastructure at a cost of Tk 750 crore. Bangladesh Army will implement it by June 2019.
The scheme got a go ahead at the Executive Committee of the National Economic Council (ECNEC), chaired by its Chief Prime Minister Sheikh Hasina. The Tuesday’s Ecnec meeting gave approval to a total of seven projects, including that of composite brigade, involving Tk 2,658 of which the government will provide Tk 2,153 crore from the national exchequer while the remaining Tk 504 crore will come as project assistance.
However, the prime minister sent back the relocation project of national secretariat at Sher-e-Bangla Nagar for further review in line with the original master plan of Jatiya Sangsad Bhaban, designed by Architect Luis I Kahn.
Until the original master plan is available, activities of the secretariat relocation project will remain held up, Planning Minister Mustafa Kamal informed, adding that they would finalise the project immediately after getting the original copy of the master plan. The meeting also approved a project namely ‘Construction of Ministers' Apartment-III’ under which 5,500 square feet flats will be built at city’s Baily Road for ministers.
The Ministry of Housing and Public Works proposed to construct 15-storied apartment involving Tk 113 crore for the ministers. But the prime minister has directed the authorities to limit the construction of the apartment to six stories, the planning minister said.
He added that the prime minister also ordered formulation of a mini-master plan for Hare Road and Minto Road so that the greenery and beauty of the areas are preserved in future.